R. L. Bowen Construction Management, LLC was hired as CM at Risk for renovations at three different sites for the Cleveland Metropolitan School District.

The first task involved the relocation of modular units from the Carl Shuler School to New Tech West and William Cullen Bryant Schools. This relocation required grading and parking improvements at all three sites.

The second task involved the construction of a pre-engineered gymnasium.

Because these projects were tightly scheduled around the summer months when the school is unoccupied, Bowen had to implement an accelerated buy-out plan to pre-qualify contractors immediately upon award of the project. The purchase order for the pre-engineered gymnasium was similarly placed as early as possible to guarantee completion in time for installation.